Lemoyne's Bridges Go Under Construction in 2027. PennDOT Planned Them to Stay Open.

What happens to a borough when both bridges connecting it to Harrisburg, plus the stretch of Market Street between them, start construction in the same year? Lemoyne finds out in 2027. PennDOT spent the past several years on designs for the I-83 South Bridge, the Market Street Bridge, and the Lemoyne Bottleneck. Read the three plans side by side and they share one goal. Each is staged so the river stays crossable while the work goes on. For drivers, that means lane shifts and detours. For walkers and cyclists, PennDOT's plans keep a path across the Market Street Bridge open the whole time.

Three projects, one starting year

The projects run on different budgets and timelines, but they converge on the same few blocks of Lemoyne.

Project What it touches in Lemoyne Anticipated start Scale
I-83 John Harris Memorial (South) Bridge Lemoyne interchange reconfigured, S. 3rd Street bridge replaced January 2027 $1.3 billion, about a decade
Market Street Bridge rehabilitation West shore approach, the western span to City Island 2027 $149 million, PennDOT lists 2034 end
Lemoyne Bottleneck Improvements Market Street from S. 3rd Street to the bridge 2027 construction season Estimates of $3.7 to $3.9 million

PennDOT's Market Street Bridge project page says the design teams for all three projects are coordinating and will keep adjusting construction timing "to determine the most appropriate overall construction schedule." The dates in the table are PennDOT's current plans and could change.

The South Bridge gets rebuilt next to itself

The I-83 South Bridge is the biggest of the three, and its construction method explains why the crossing stays open. According to PennLive's August 2026 coverage, PennDOT Secretary Michael Carroll laid out the sequence:

  1. Build a new bridge just south of the existing one and move all traffic onto it.
  2. Tear down the old bridge.
  3. Build a second new bridge where the old one stood.
  4. Run I-83 northbound and southbound on the two new bridges.

Carroll said he hopes the first new bridge can be built in about four years, and that the whole project will take about a decade. On traffic during construction, he said:

"We will do our best to minimize it. Likely there'll be two lanes in each direction the bulk of the time during the period of construction. There may be intermittent detours for some of the ramps."

Those ramp detours are where the work comes closest to Lemoyne. The scope includes reconfiguring the Lemoyne interchange and replacing the South Third Street bridge in Lemoyne. PennDOT puts traffic on the current bridge at more than 125,000 vehicles a day. On the project page, the detours link still reads "Coming Soon."

On Market Street, cars lose one direction at a time

The Market Street Bridge connects Lemoyne and Wormleysburg to City Island and on to downtown Harrisburg. PennDOT's plan keeps all four 10-foot travel lanes once the work is done. That wasn't always the plan. TheBurg reported in August 2026 that a 2025 version of the design dropped one lane in each direction. Concerns about traffic flow and access to City Island led PennDOT to restore all four. Project Manager Pharon Bertsch said part of the reasoning was that "if there was ever maintenance that needs done to the Harvey Taylor structure, we would have the four lanes available for Market Street that could be used as an alternate route."

During construction, the Harvey Taylor Bridge plays the same backup role in reverse. PennDOT's phasing plan:

  • Phases 1A and 1B: Build the new utility bridge and move all utilities onto it. Existing lanes stay open apart from short-term closures.
  • Phases 2A to 2C: Rebuild the downstream side. One westbound lane stays open, and all eastbound traffic toward Harrisburg is detoured via the Harvey Taylor Bridge.
  • Phases 3A to 3C: Rebuild the upstream side. One eastbound lane stays open, and all westbound traffic toward Lemoyne is detoured via the Harvey Taylor Bridge.
  • Phases 4A and 4B: Full-depth paving near both shore intersections and across City Island, with the same one-direction pattern.

City Island stays reachable throughout. PennDOT says two-way traffic will be kept between each shore and the island, and island access from each shore will be kept throughout. The exception is 4A and 4B, when the island is reached from one shore at a time. In practice, a Lemoyne driver headed to a Senators game during Phase 2 can still drive onto the island from the west shore. The detour applies only to continuing on to downtown Harrisburg. Bus stops and parking lots on City Island stay open in every phase. Senators President Kevin Kulp told TheBurg, "People are going to be able to access the island from both directions and we are going to do everything we can to minimize the effects so that it doesn't impact their experience."

The walking route across the river stays open

Walkers and cyclists keep the most continuous access in the Market Street plan. That starts from a limited baseline. PennDOT's project page says the western span, the one between Lemoyne and City Island, now has two sidewalks just 4 feet 7 inches wide. The downstream sidewalk on that span is closed because of the condition of the beams underneath.

The first piece of construction is a separate utility bridge built just downstream. It will carry the gas, fiber optic, and sewer lines that now run under the sidewalks. It will also carry a 14-foot bicycle and pedestrian path. PennDOT estimates the utility bridge at $14 million to build. Moving the utilities before any lanes close avoids an estimated 4 to 6 extra years of traffic impacts.

The timing works in walkers' and cyclists' favor. PennDOT says the existing upstream sidewalk stays open while the downstream side is rebuilt, and the utility bridge opens during Phase 3, when work moves to the upstream side. The 14-foot path opens at the same point the upstream sidewalk comes under construction. When the work is done, the western span gets a 7-foot upstream sidewalk, more than 2 feet wider than today's, plus 2-foot shoulders on both sides. Shared-lane markings and "Bicycles Allowed Use of Full Lane" signs will run from shore to shore.

TheBurg reports that construction is slated to begin in summer 2027. The utility bridge would take the first two years, followed by four years of work on the main bridges. PennDOT's own page gives a 2027 start and a 2034 end.

The quarter mile between Third Street and Front Street

The Lemoyne Bottleneck is where the bridge approach meets the borough. It's the roughly 0.4-mile curve of Market Street between South Third Street and the bridge. PennDOT lists the problems it targets: heavy traffic, a curving alignment, limited sight distance, inconsistent or missing shoulders, and narrow sidewalks in poor condition, especially at the Norfolk Southern railroad bridges.

The alternative PennDOT recommended, Alternative 2, would make these changes:

  • Lanes become one eastbound and two westbound, with 11-foot minimum lanes and a 3-foot shoulder.
  • 8-foot-wide shared-use paths are raised 8 inches on both sides of Market Street.
  • Emergency-vehicle signal preemption is added at both the Front Street and Third Street intersections.
  • Fewer lanes run in front of the Penn State Health Life Lion EMS facility, and a pull-off space is added on the approach to Front Street.

PennDOT's project page says the project is in final design "on the selected alternative" but doesn't name which one. The Market Street Bridge page says the two projects will be coordinated so the improvements connect. If Alternative 2 is the design that gets built, shared-use paths on Market Street would lead to a wider upstream sidewalk and a separate 14-foot path across the river.

Construction follows the same approach as the bridges. PennDOT expects several stages, with possible short-term partial or weekend detours. Pedestrian and bike access through the corridor stays open, and access to adjacent businesses and Life Lion EMS will be maintained. The nearest riverfront restaurants are on Front Street just off the corridor. Dockside Willies is at 449 South Front Street in Lemoyne, and Dukes Riverside is at 313 South Front Street in Wormleysburg.

What gets decided this fall

Some of this is already scheduled. Other pieces are still open as of early October 2026:

  • October 29, 2026: Bids are due for the I-83 South Bridge construction contract.
  • November 2026: Carroll said the contract would be awarded this month. No contractor has been named yet.
  • January 2027: Expected start of South Bridge construction. PennDOT's project page lists a start date but no completion year.
  • Lemoyne Bottleneck: PennDOT's project description listed an August 2026 contractor bid date. PennDOT's August 19, 2026 notice still described the project as in design, with construction estimated for 2027. That notice also covered survey and utility-locating work on Market and Front Streets from August 24 to 29.

PennDOT says details for each project will be posted on its District 8 website. The South Bridge page already has a placeholder for detours, marked "Coming Soon."

If you're thinking about a move in or around Lemoyne over the next few years, I'm keeping track of these construction schedules and can explain what each phase means for the streets around a particular home. David K Hawkins is glad to walk through it with you. Let's Connect.

Work With David

From coordinating mortgage, title, and insurance to addressing potential issues early, I strive to deliver results with integrity and professionalism. When you choose to work with me, you gain a partner committed to your success.

Follow Me on Instagram