On a Friday in late October, a Sentinel photographer stood on East High Street and photographed what the former Frog, Switch & Manufacturing Co. site at 600 E. High St. now looks like. The ground has been cleared for cleanup, remediation and whatever gets built next. One structure is still standing, the company's office building.
That building was kept on purpose. The cleanup group plans to restore it, the borough has talked with the demolition contractor about salvaging pieces of the plant, and the development concept for the 27 acres ties the site back into the surrounding street grid and the houses next to it. The demolition machines are gone. What happens next will depend on what has been saved.
The building that stays
The office building is a Spanish Mission-style structure facing East High Street. In August 2026, the Cumberland Area Economic Development Corp.'s board minutes described a scope of work for it covering abatement, a new roof and waterproofing. The plan removes the flat-roofed additions built onto it over the years and keeps the original structure.
The same minutes say a Rails to Trails Council has shown "strong interest" in partnering on the building, along with other community groups. In its fall reporting, The Sentinel noted that the office building was still standing as the rest of the site was cleared.
Other pieces of the plant are being saved too:
- Salvaged pieces. Carlisle Borough met with the demolition contractor, F.R. Beinke, to discuss saving select pieces of the site "to preserve as part of Frog Switch's legacy."
- Foundry molds. According to the project FAQ, the Real Estate Collaborative is saving some of the company's molds, which could be cast in concrete as sculptures along a walking path if one is built on the site.
- Company records. The Cumberland County Historical Society holds the company's archival materials.
What the plant was
That history reaches back almost two centuries. According to the history page on CAEDC's Frog Switch microsite, industry on this stretch of East High Street goes back further than the company name:
- 1840. Franklin Gardner opened a foundry and machine shop at East High and Bedford streets that built steam engines, grain drills and rail cars.
- 1884. Carlisle Manufacturing began making railroad frogs and switches, the track parts that guide trains from one rail onto another.
- 1898. John Hays and associates formed a company centered on those railroad parts.
- 1907. The Frog, Switch & Manufacturing Co. name was adopted.
- By 1913. A manganese-steel foundry had been added. The plant later made manganese-steel castings for crushers.
- June 30, 2023. Production ended, with about 30 workers remaining. At its peak, the company employed around 240 people.
Carlisle rezoned the property Urban Mixed Use in 2023 and changed its comprehensive-plan designation to Urban Redevelopment, according to the borough. The Real Estate Collaborative, a volunteer-run subsidiary of CAEDC formed in 2016 to reuse underused properties in Cumberland County, took ownership of the site in spring 2025.
How the buildings came down in 2026
Even the demolition went through a preservation debate. PennLive reported in February that Carlisle had passed a new ordinance requiring developers at qualifying Urban Mixed Use sites to show, with financial documentation, that reusing large industrial buildings was not feasible before tearing them down. The collaborative had filed its demolition application the day before that ordinance took effect on Jan. 8.
The borough rejected the application because it lacked proof of the demolition contractor's liability insurance. The collaborative argued that proof could follow once a contract was awarded. The Board of Appeals unanimously voided the denial and sent the application back to be reconsidered under the older code.
After that ruling, work went quickly. By late August, the long building known as the Frog Shop had been fully demolished, and about 75,000 gallons of oil had been recovered from equipment beds. Crews had removed the foundry's transite roof, and that building was being taken down. At its Sept. 18 meeting, the REC Management Group recorded that demolition was complete, the last buildings had been brought down to grade, and the site was in its cleanup phase. Foundry sand removal was scheduled to start the following week and last at least two weeks, with little expected effect on road traffic. The receiving landfill had tested and approved the material.
Most of the cleanup is paid for with state money:
| Item | Amount | Source |
|---|---|---|
| PA SITES award, total | $10,227,830 | State grant and loan |
| PA SITES grant portion | $6,136,698 | |
| PA SITES loan portion | $4,091,132 | |
| Industrial Sites Reuse Program loan | $750,000 | Closed July 30, 2026 |
| Demolition contract, F.R. Beinke | $815,975.58 | |
| Environmental remediation contract, Retro Environmental LLC | $463,960 |
The demolition and remediation contracts together come to roughly $1.28 million, about an eighth of the PA SITES award. The state money was meant for more than clearing the land. According to the collaborative, its purpose is to make the site pad-ready so it can be sold to a developer.
What the 27 acres could become
When the collaborative asked developers for qualifications in spring 2026, its request for qualifications listed the goals: a mixed-use community with jobs and business growth, streets, parks, plazas, open space, food and beverage destinations, and access for walking, biking and driving.
The same document includes a full-reuse concept carried over from earlier planning. It is a sketch, not a selected proposal, and it lays out the site in pieces:
- Along East High Street: mixed-use buildings that could face the sidewalk if retail is viable, or sit farther back if residential demand is stronger.
- Inside the site: a road network that could be fully upgraded and connected to the surrounding street grid.
- On the east side: some housing oriented toward the existing residential neighborhood.
- In the northeast: more active recreation, with open space and trails over the former landfill.
- West of Shaffner Avenue: a smaller commercial infill site at the corner.
The RFQ also mentions a possible Louther Street extension, which would need its own funding. It notes that East High Street is a state road, SR 641, so changes at the Shaffner Avenue intersection or the site driveways would require coordination with PennDOT and possibly a highway occupancy permit and traffic study. Under that concept, a factory that sat apart from the neighborhood for more than a century would gain streets, sidewalks, homes and paths that link it to the blocks around it. The saved office building would stand at the front of that layout on East High Street.
The next steps for the site
At the Sept. 18 meeting, the REC Management Group voted to negotiate a letter of intent with development partners. The group discussed writing in requirements tied to PA SITES and zoning, along with clear milestone dates, especially a six-month timeline to settlement. The Sentinel later reported that the collaborative was still negotiating with two local companies interested in redeveloping the site.
Several more decisions follow from that negotiation:
- The developer agreement. A letter of intent with a six-month milestone to settlement.
- The North Middleton acres. About 5 acres of the property are in North Middleton Township. Whether they join the overall plan or are split off and sold separately depends on which developer is chosen.
- Finishing the ground work. The RFQ targets the first quarter of 2027 for completing environmental remediation and demolition. A geotechnical study of foundation heights and composition was commissioned ahead of the second phase of demolition.
- Building, eventually. CAEDC's project page puts the overall timeline at anywhere from three to 10 years, depending on environmental findings, land development approvals, permits and funding.
The public can follow these decisions as they happen. The collaborative's Community Involvement Plan says its monthly Management Group meetings are open to the public, and that it will keep posting updates on its website and social media and issue the required cleanup notices while it owns the property. Minutes, agendas, the environmental reports and the RFQ are posted on the Frog Switch microsite. The developer agreement, the office building's future use and the walking path are the next decisions on the agenda. For more about the rest of town this season, our Carlisle neighborhood page and our post on what's changing in downtown Carlisle this year cover the blocks west of the site.
If you own a home near East High Street and want to talk about what a project like this could mean for your property over the next few years, David K Hawkins is glad to follow the Frog Switch record with you and keep you informed as decisions are made. Let's Connect.